Road Paving Schedule

Road Paving Is Complete!
Posted on 07/27/2022

The Wilton DPW and Advanced Paving would like to thank the Wilton residents for their patience and cooperation while we did all the reclaim and paving work.

With all your help the job went smooth and in a timely manner.  Thank You!

DPW Director, Mike Tatro




August 1 Update
Paving will begin on Pine Valley tomorrow.

July 28th Update:

Work begins on Pine Valley Street today, and Maple Street will be paved on Friday.

July 27th Update:
Tomorrow paving starts on Burns Hill Road, as does the reclamation of Maple Street.

July 21st Update:
Paving will start on Pleasant Street.

July 20th Update:

Paving will begin tomorrow on Burns Hill rd. from Island Street to Holt Hill.

On Monday July 18th paving will take place on Isaac Frye Highway between Route 31 and Burton Highway.  There will be no thru traffic allowed while that street is being worked on as it is too narrow.

UPDATE: as of 7/20, the paving has been completed but the crew will be finishing up the matching to the driveways tomorrow.

The following additional roads will be scheduled for paving this summer:

  • Pine Valley Street
  • Pleasant Street
  • Maple Street from Main Street to Park Street
  • Burns Hill from Island Street to Holt Hill

Check back here for future updates!